在門(mén)式腳手架行業(yè)當(dāng)中,門(mén)式腳手架是應(yīng)用最為多的一種,也是備受大家歡迎的一種。門(mén)式腳手架的規(guī)范標(biāo)準(zhǔn)情況怎么樣呢?在搭設(shè)之后驗(yàn)收不可少,這是非常重要的一項(xiàng),否則不可靠的移動(dòng)腳手架搭設(shè),可能會(huì)造成人身財(cái)產(chǎn)等方面的損失,還需要格外當(dāng)心了,盡量避免了。高度在20m及20m以下的移動(dòng)腳手架,由單位工程負(fù)責(zé)人組織技術(shù)安全人員進(jìn)行檢查驗(yàn)收;高度大于20m的腳手架,由工程處技術(shù)負(fù)責(zé)人隨工程進(jìn)度分階段組織單位工程負(fù)責(zé)人及有關(guān)的技術(shù)安全人員進(jìn)行檢查驗(yàn)收。
In the portal scaffolding industry, portal scaffolding is one of the most widely used and popular. What is the standard condition of portal scaffolds? Acceptance is indispensable after erection, which is a very important one. Otherwise, unreliable mobile scaffolding erection may cause personal and property losses, but also need to be extra careful to avoid as far as possible. Scaffolds with height below 20m and 20m shall be inspected and checked by the technical safety personnel in charge of the unit project; scaffolds with height above 20m shall be inspected and checked by the technical personnel in charge of the unit project and relevant technical safety personnel in stages according to the progress of the project. 門(mén)式腳手架驗(yàn)收時(shí)應(yīng)具備下列文件:必要的施工設(shè)計(jì)文件及組裝圖;腳手架部件的出廠(chǎng)合格證或質(zhì)量分級(jí)合格標(biāo)志;腳手架工程的施工記錄及質(zhì)量檢查記錄;移動(dòng)腳手架搭設(shè)的重大問(wèn)題及處理記錄;移動(dòng)腳手架工程的施工驗(yàn)收?qǐng)?bào)告。
When accepting portal scaffolding, the following documents should be provided: necessary construction design documents and assembly drawings; manufacturer's qualification certificate of scaffolding components or quality grading qualification marks; construction records and quality inspection records of scaffolding projects; major problems and treatment records of scaffolding erection; construction acceptance reports of scaffolding projects.
門(mén)式腳手架工程的驗(yàn)收,除查驗(yàn)有關(guān)文件外,還應(yīng)進(jìn)行現(xiàn)場(chǎng)抽查。
In addition to checking relevant documents, the acceptance of portal scaffold works should be carried out on-site spot checks.
抽查應(yīng)著重以下各項(xiàng),并記人施工驗(yàn)收?qǐng)?bào)告:安全措施的桿件是否齊全,扣件是否緊固、合格;安全網(wǎng)的張掛及扶手的設(shè)置是否齊全;基礎(chǔ)是否平整堅(jiān)實(shí);連墻桿的設(shè)置有否遺漏,是否齊全并符合要求;垂直度及水平度是否合格。
Spot check should focus on the following items, and record the construction acceptance report: whether the rods of safety measures are complete, whether fasteners are tightened and qualified; whether the safety net and handrails are set up completely; whether the foundation is smooth and solid; whether the connecting rods are set up missing, whether they are complete and meet the requirements; whether the vertical and horizontal degrees are in line with the requirements; Ge.
門(mén)式門(mén)式腳手架的水平度:底步門(mén)式腳手架沿墻的縱向水平偏差應(yīng)L/600(L為梯形腳手架的長(zhǎng)度)。門(mén)式梯形腳手架搭設(shè)尺寸允許偏差:腳手架的垂直度:腳手架沿墻面縱向的垂直偏差應(yīng)H/400(H為腳手架高度)及50mm;腳手架的橫向垂直偏差H/600及50mm;每步架的縱向與橫向垂直度偏差應(yīng)ho/600(h2為門(mén)架高度)。
Level of portal scaffolding: The vertical horizontal deviation of the bottom scaffolding along the wall should be L/600 (L is the length of the scaffolding). The allowable deviation of scaffolding dimensions: the vertical deviation of scaffolding: the vertical deviation of scaffolding along the wall should be H/400 (H is scaffolding height) and 50mm; the horizontal vertical deviation of scaffolding should be H/600 and 50mm; the vertical and horizontal deviation of each scaffold should be ho/600 (h2 is the height of the scaffold).
門(mén)式腳手架的規(guī)范標(biāo)準(zhǔn)目前國(guó)家已經(jīng)有了一定的規(guī)定,大多數(shù)正規(guī)而專(zhuān)業(yè)的生產(chǎn)、出售或是租賃腳手架的公司,都有相關(guān)的規(guī)定,并會(huì)按照相關(guān)的要求去生產(chǎn)。在搭設(shè)的時(shí)候,也要按照規(guī)范來(lái)執(zhí)行的。
我廠(chǎng)腳手架銷(xiāo)售遍布全國(guó)各地 贏(yíng)得了廣大用戶(hù)的認(rèn)可